Construction Photos - Week of 04/09/10
Contractor backfilling in Quad "D" and Quad "A"
Looking south from north side of the hill over the Sedimentation Basin Nos. 1 & 2 and the Maturation Basin Nos. 1 & 2
Looking west along the north walls of Maturation Basin #1 and Sedimentation Basin #1
On top of the north hill looking south across the west side of Quad "D"
On top of north hill looking SE over Quad "D"
Forming for wall in the future Filtered Effluent Pump Station
Looking SW across the NW area of Quad "D"
Looking SE across the NW area of Quad "C"
Getting ready to set rebar mats in the area for Maturation Basin Nos. 1 & 2 and Sedimentation Basin Nos. 1 & 2
Setting rebar mats along the north side of Quad "D" for Maturation Basin No. 1 and Sedimentation Basin No 1
Interior wall in Quad "C" for the future Filtered Effluent Pump Station. See sht 3-A-2
Testing the Raw Water Collection Effluent Box going between steel pipe and PVC pipe
PVC and steel pipe of the Raw Water Collection Effluent Box
42" RW piping coming up thru the floor as shown on sht 3-M-3
North Dakota testing for compaction in the area of Quad "A"
Pumping the bases for the two 6" SSL piping going to be encased, two lines to drain / decant pump station
Pouring the bases for the two 6" SSL piping going north to south
Pouring the bases for the two 6" SSL piping. See sht 3-M-4
Base supports for the two 6" SSL piping going north to south, see sht 3-M-4
Forming for the 48" RW steel pipe and PVC 48", see sht 3-M-3
Forming the 48" piping going north from the NW corner of the water plant
Steel and PVC 48" piping being installed together as shown on sht 3-M-2
Installing the 48" PVC piping together, see sht 3-M-3
Installing 48" PVC piping together on the NW corner of the water treatment plant, getting ready to install the test station
Getting ready to install the test station with galvanic anodes, see sht 3-M-2 and detail 13933 (see sht 13930)
Finishing forming the 48" piping and 48" PVC piping at the NW corner
Visitors on project site this date in the Water Treatment Clearwell
Visitors on project site this date in the Water Treatment Clearwell
Galvanic anodes on east side of the piping as shown, NW corner of the building area
Anodes and forms for pipe encasement as shown on sht 3-M-3
All the wiring for the anodes and wiring on the outside of the forming, see sht 3-M-3
See wiring, anodes on the 48" PVC piping, see sht 3-M-3
Looking north from the south area of the location of the two 6" SSL piping, see sht 3-M-4
6" piping for the SSL piping
Contractor setting the 6" SSL being set and getting ready to encase in concrete
Contractor pouring the walls on the future filter, see sht 3-M-9
Piping openings in the SE corner area
Pouring the interior wall in the north side of the future Filter Effluent Pump Station
Two 6" SSL piping going north to south, getting ready for encasement forming
Rebar in the area of the floor area of the Maturation Basins and Sedimentation Basin No. 1
Pouring wall in the area of filter #8
Walls being formed on the south side of filters #5 thru #8
Encasing the 48" piping on the NE corner of the project site
Pouring the 48" piping next to the 42" piping on the NE corner of the Raw Water
Stripping the forms on the NE corner of the 48" piping
Forming the two 6" SSL piping going north to south
Pouring the floor and outside walls for Maturation Basins #1 and #2 along with Sedimentation Basins # 1 and #2
Re-shoring the stub wall in the SE corner of Sedimentation Basin No. 2
Pouring the supports for the two 6" SSL piping going north to south
Forms for the two 6" SSL piping going north to south, see sht 3-M-4
Thumbnail panels:
|
|
|