Construction Photos - Week of 03/05/10
Doing forming work on the walls, NE corner area for future Treatment UV area
Working on forming for the NE corner of the future Treatment UV area
Forming for the center area of the east end of the future filter Effluent Pump Station
Looking from the west to the east in the area for the Quad "D"
Working on the 42" FE going thru the wall with the wall piping
Inside NE corner area of the 42" FE piping and other opening along the forming for 24" BWW, 16" FTW and 24" BWS piping
Contractors wall in their office area on information for the workers including contractor personnel information
Contractors wall in their office area on information for the workers including contractor personnel information
Area with ground heaters heating the ground for another lift in Quad "D". See sht 3-S-12
Working on the NW south wall on the forming and trying rebar mats for the 24" BWW, 16" FTW and 24" BWS piping on east wall
Working on forming for the 42" FE piping in the NE corner of the east wall
Back filling on compacting lifts for the Quad "D" area
Contractor having piping being unloaded on the project site
Contractor having piping being unloaded on the project site in various locations
Unloading various sections of piping on the project site
Forming and doing the piping on the NE corner for the 42" FE piping, 24" BWW, 16" FTW and 24" BWS
Unloading and stockpiling piping in the center area of the main Treatment Building
Opening the sleeves for the 24" BWS, 16" FTW and 24" BWS, see sht 3-M-13
Setting the cat walks on the top of the walls on the west and north sides of forming
Finished the forming for the openings sleeves
Finishing forming on setting sleeves for the 24" BWM, 16" FTW and 24" BWS piping in the NE corner area
Finishing forming the last section of the north wall section west side going east
Setting the 42" wall piping in the NE corner of the FE piping
Patching with forms the last section of wall to be finished at this time
Contractor getting north wall set for the pour next Monday, 3/8/10
Contractor setting the 42" FE piping in the NE corner of the future UV Disinfection Unit
Finishing setting the 24" BWW, 16" FTW and 24" BWS for the next pour on Monday, 3/8/10
Compaction on the Quad "D" area, 98%
Testing lab doing a density test in the area outside the 10' 95% compaction (only need 95% in this area)
On the top of the hill to the NE of the main Treatment building, looking SW across the building area
Piping on the project site
Looking south from the hill north of the project site, looking at the main Treatment building
Contractor getting ready to paint tar on the walls, 30" ± higher than before
Keeping the heat inside the plastic cover so they can keep on backfilling and compacting, along with testing
Keeping everything warm for the tar wall painting
Marking area where they want to tar the existing wall, 2 coats
Setting the last east wall section of the south end section of this pour where the 24" BWS comes out of the walls
Setting the last east wall section on the south end section on this pour where the 24" BWS piping goes
Painting the next section 30" ± on the west wall of the Filter #5
NE corner area getting ready for pour next Monday, 3/8/10