| |
Construction Photos - Week of 02/26/10
Coating with water proofing (HLM 5000) on the west wall of Filter #5
Coating with water proofing (HLM 5000) on the west wall of Filter #5 and wall going south to north
9' I going east from NW corner of Filter #5 for water proofing
Inside the south wall of the future filter Effluent Pump Station, looking east to west
Piping thru the north / SE wall for future filter Effluent Pump Station
Covering the fill area for the fill in the Quad "D" footing / foundation floor area
Removing the heating piping in the area where the blankets covered the ground, not where the snow is.
Contractor has the walls covered for heating on Filters #1 and #5
Heater coils on the ground west of the Filters #1 and #5
The area west of the Filter #1 and #5 going west, heater hose is 7/8", north
The area west of the Filter #1 and #5, going west, removing the cover blanket
Working on heating the ground in Quad "D" floor and footing area going east to west
The area west of the Filter #5 and Filter #1 going west from the east
The area for Quad #4 backfilling going from elevation 1985.0±
Getting area ready for testing in area ready to start backfilling up to elevation 1905.
Still working on getting area on the west wall of Filter Basin #5 (note: got leak stopped)
Getting the insulation (2") to be put between outside walls and backfilled against them with gravel
Installing the 2" insulation on the west side of the Filter #5 and #1 with the pipe gallery between #5 and #1
Installing the rest of the rebar in the top of the south (east/west) wall for the filter Effluent Pump Station
Getting leaking crack in the west wall of Filter #5
Set up with pumper truck and are pouring exterior wall of the future filter Effluent Pump Station
Pumping concrete wall pour for the future Filter Effluent Pump Station
Contractor receiving piping for project site
Contractor stock piling piping on the north side of the project site
Contractor is removing piping from project site and adding other piping to project site
Stock piling being removed and new piping being stock piled
Getting ready to water proof the west wall leak area of the Filter #5
Contractor fixing leak area on the west wall of Filter #5, not leaking at this time
Looking into the filter piping gallery east to west
Fixing the rebar for the 24" piping opening in the Filter #8
Fixing the rebar area for the 24" piping in Filter #8
Piping being stock piled on the SE corner area of project site behind the Water Recovery Basin
Thumbnail panels:
|
|
|