Construction Photos - Week of 02/26/10

  • Image
    Coating with water proofing (HLM 5000) on the west wall of Filter #5
  • Image
    Coating with water proofing (HLM 5000) on the west wall of Filter #5 and wall going south to north
  • Image
    9' I going east from NW corner of Filter #5 for water proofing
  • Image
    Inside the south wall of the future filter Effluent Pump Station, looking east to west
  • Image
    Piping thru the north / SE wall for future filter Effluent Pump Station
  • Image
    Covering the fill area for the fill in the Quad "D" footing / foundation floor area
  • Image
    Removing the heating piping in the area where the blankets covered the ground, not where the snow is.
  • Image
    Contractor has the walls covered for heating on Filters #1 and #5
  • Image
    Heater coils on the ground west of the Filters #1 and #5
  • Image
    The area west of the Filter #1 and #5 going west, heater hose is 7/8", north
  • Image
    The area west of the Filter #1 and #5, going west, removing the cover blanket
  • Image
    Working on heating the ground in Quad "D" floor and footing area going east to west
  • Image
    The area west of the Filter #5 and Filter #1 going west from the east
  • Image
    The area for Quad #4 backfilling going from elevation 1985.0±
  • Image
    Getting area ready for testing in area ready to start backfilling up to elevation 1905.
  • Image
    Still working on getting area on the west wall of Filter Basin #5 (note: got leak stopped)
  • Image
    Getting the insulation (2") to be put between outside walls and backfilled against them with gravel
  • Image
    Installing the 2" insulation on the west side of the Filter #5 and #1 with the pipe gallery between #5 and #1
  • Image
    Installing the rest of the rebar in the top of the south (east/west) wall for the filter Effluent Pump Station
  • Image
    Getting leaking crack in the west wall of Filter #5
  • Image
    Set up with pumper truck and are pouring exterior wall of the future filter Effluent Pump Station
  • Image
    Pumping concrete wall pour for the future Filter Effluent Pump Station
  • Image
    Contractor receiving piping for project site
  • Image
    Contractor stock piling piping on the north side of the project site
  • Image
    Contractor is removing piping from project site and adding other piping to project site
  • Image
    Stock piling being removed and new piping being stock piled
  • Image
    Getting ready to water proof the west wall leak area of the Filter #5
  • Image
    Contractor fixing leak area on the west wall of Filter #5, not leaking at this time
  • Image
    Looking into the filter piping gallery east to west
  • Image
    Fixing the rebar for the 24" piping opening in the Filter #8
  • Image
    Fixing the rebar area for the 24" piping in Filter #8
  • Image
    Piping being stock piled on the SE corner area of project site behind the Water Recovery Basin
  • Image
    Patching the opening for the 24" piping in Filter #8
Thumbnail panels:
Now Loading

 

 
Home
Water Treatment Plant Phase 1 Construction:   Construction Photos     Daily Construction Logs
Water Treatment Plant Phase 2 Construction:   Construction Photos     Daily Construction Logs
Lagoon:   Construction Photos     Daily Construction Logs