Construction Photos - Week of 11/28/08

  • Image
    Looking at the pipe collars on the 48” and 36” FE pipes on the west end of the Contact Basin
  • Image
    Thrust block subgrade for 24” FW pipes
  • Image
    NE corner of the Clearwell electric room
  • Image
    View along north CMU wall of the Clearwell electric room
  • Image
    View along east CMU wall of the Clearwell electric room
  • Image
    BWR water recycle pump base reinforcement
  • Image
    BWR water recycle pump base pad forms
  • Image
    24” backwash waste and 16” filter to waste piping on the north side of the BWR
  • Image
    24” backwash waste and 16” filter to waste piping on the north side of the BWR
  • Image
    24” backwash waste and 16” filter to waste piping on the north side of the BWR
  • Image
    North Clearwell wall waterproofing
  • Image
    North Clearwell wall waterproofing
  • Image
    North Clearwell wall waterproofing
  • Image
    North Clearwell wall waterproofing
  • Image
    View of the 24” FW pipes
  • Image
    View of the 24” FW pipes
  • Image
    View of the power duct bank on the south side of the BWR Basin
  • Image
    View of the electrical conduit on the north side of theBWR
  • Image
    Looking east along the north side of the Clearwell and Contact Basin
  • Image
    Looking west along the north side of the Clearwell and Contact Basin
  • Image
    View of the FE pipes on the west end of the Contact Basin
  • Image
    View of the FE pipes on the west end of the Contact Basin
  • Image
    View of the NE corner of the Clearwell
  • Image
    Looking west along the north Clearwell wall
  • Image
    Looking east along the north wall of the Clearwell and Contact Basin
  • Image
    Filter Effluent piping on the west end of the Contact Basin
  • Image
    Filter Effluent piping on the west end of the Contact Basin
  • Image
    Looking east along the north wall of the Clearwell and Contact Basin
  • Image
    View of the west Contact Basin wall from the NW corner
  • Image
    View of the north side of the Clearwell from the NE corner
  • Image
    View of the east side of the Clearwell from the NE corner
Thumbnail panels:
Now Loading

 

 
Home
Water Treatment Plant Phase 1 Construction:   Construction Photos     Daily Construction Logs
Water Treatment Plant Phase 2 Construction:   Construction Photos     Daily Construction Logs
Lagoon:   Construction Photos     Daily Construction Logs