Construction Photos - Week of 11/07/08

  • Image
    Looking at the backfill on the south side of the BWR Basin
  • Image
    Looking at the backfill on the west side of the BWR Basin
  • Image
    View of the south Clearwell CMU wall from the SW corner
  • Image
    View of the west Clearwell CMU wall from the SW corner
  • Image
    View of the north Clearwell CMU wall from the NW corner
  • Image
    Looking at the backfill on the west side of the BWR Basin
  • Image
    Clockwise view of the exterior Clearwell walls during the leak test starting at the NW corner and going to the SW corner (1 of 12)
  • Image
    Clockwise view of the exterior Clearwell walls during the leak test starting at the NW corner and going to the SW corner (2 of 12)
  • Image
    Clockwise view of the exterior Clearwell walls during the leak test starting at the NW corner and going to the SW corner (3 of 12)
  • Image
    Clockwise view of the exterior Clearwell walls during the leak test starting at the NW corner and going to the SW corner (4 of 12)
  • Image
    Clockwise view of the exterior Clearwell walls during the leak test starting at the NW corner and going to the SW corner (5 of 12)
  • Image
    Clockwise view of the exterior Clearwell walls during the leak test starting at the NW corner and going to the SW corner (6 of 12)
  • Image
    Clockwise view of the exterior Clearwell walls during the leak test starting at the NW corner and going to the SW corner (7 of 12)
  • Image
    Clockwise view of the exterior Clearwell walls during the leak test starting at the NW corner and going to the SW corner (8 of 12)
  • Image
    Clockwise view of the exterior Clearwell walls during the leak test starting at the NW corner and going to the SW corner (9 of 12)
  • Image
    Clockwise view of the exterior Clearwell walls during the leak test starting at the NW corner and going to the SW corner (10 of 12)
  • Image
    Clockwise view of the exterior Clearwell walls during the leak test starting at the NW corner and going to the SW corner (11 of 12)
  • Image
    Clockwise view of the exterior Clearwell walls during the leak test starting at the NW corner and going to the SW corner (12 of 12)
  • Image
    View of the south BWR wall from the SW corner
  • Image
    View of the north BWR wall from the NE corner
  • Image
    View of the 36” and 48” FE pipe stub outs on the west end of the Contact Basin
  • Image
    View of the BWR Basin upper slab shoring and supports from on top of the BWR Masonry building
  • Image
    View of the BWR Basin upper slab shoring and supports from on top of the BWR Masonry building
  • Image
    Looking west at the Clearwell CMU walls from on top of the BWR Pump Room building
  • Image
    Looking at the stub outs on the west end of the Contact Basin
  • Image
    Looking east at the Clearwell CMU walls
  • Image
    View to the north of the BWR Basin upper slab east beam pocket
  • Image
    View to the south of the BWR Basin upper slab east beam pocket
  • Image
    View to the north of the BWR Basin upper slab west beam pocket
  • Image
    View of the BWR Basin upper slab from the south to north (1 of 4)
  • Image
    View of the BWR Basin upper slab from the south to north (2 of 4)
  • Image
    View of the BWR Basin upper slab from the south to north (4 of 4)
  • Image
    View of the BWR Basin upper slab from the south to north (3 of 4)
  • Image
    Looking west at the Clearwell CMU walls from on top of the BWR Pump Room building
  • Image
    Looking south at the BWR Pump Room roof steel decking
  • Image
    Looking north at the BWR Pump Room roof steel decking
  • Image
    Looking at the roof scupper in the BWR Pump Room building east wall
  • Image
    Looking at the roof scupper in the BWR Pump Room building east wall
  • Image
    Looking at the roof joists and decking from inside the BWR Pump Room building
  • Image
    Looking at the roof joists and decking from inside the BWR Pump Room building
  • Image
    East to west panoramic view of the site from on top of the 3:1 slope (1 of 10)
  • Image
    East to west panoramic view of the site from on top of the 3:1 slope (2 of 10)
  • Image
    East to west panoramic view of the site from on top of the 3:1 slope (3 of 10)
  • Image
    East to west panoramic view of the site from on top of the 3:1 slope (4 of 10)
  • Image
    East to west panoramic view of the site from on top of the 3:1 slope (5 of 10)
  • Image
    East to west panoramic view of the site from on top of the 3:1 slope (6 of 10)
  • Image
    East to west panoramic view of the site from on top of the 3:1 slope (7 of 10)
  • Image
    East to west panoramic view of the site from on top of the 3:1 slope (8 of 10)
  • Image
    East to west panoramic view of the site from on top of the 3:1 slope (9 of 10)
  • Image
    East to west panoramic view of the site from on top of the 3:1 slope (10 of 10)
Thumbnail panels:
Now Loading

 

 
Home
Water Treatment Plant Phase 1 Construction:   Construction Photos     Daily Construction Logs
Water Treatment Plant Phase 2 Construction:   Construction Photos     Daily Construction Logs
Lagoon:   Construction Photos     Daily Construction Logs