| |
Construction Photos - Week of 03/20/09
Trenching for 24” culvert for new approach to entrance to plant site
Trenching for 24” culvert for new approach to entrance to plant site, trenching north to south
Looking north to south for new 24” culvert crossing at entrance to the project site
Type of material from the existing trench at entrance to project site
Roofing contractor and the masonry contractor working on the roof of the Clearwell Reservoir / Finished Water Pump Station
West 24”Ø FW 90º bend. See shts 4-M-1 and 2-C-11
Pipe drainage on the north most wall in the Clearwell
Grouting the floor section in lower level of the Clearwell Pump Station between columns C & D (north side)
See sht 2-C-4 on new 24ӯ culvert at approach into water treatment plant
Existing underground utilities crossing new 24ӯ CMP at entrance to the water treatment plant
Bedding and backfilling on the 24ӯ CMP at approach to the water treatment plant
Looking SW of the job site from the roof of the Clearwell Finish Water Pump Station
Looking NW of the job site from roof of the Clearwell Finish Water Pump Station
Concrete pad forms at pump locations on the east wall area of the Clearwell Water Pump Station
Trenching for the 24ӯ CMP entrance to the water treatment plant site, looking south
Trenching for an outlet drainage where the new trench will go for future approach
Pouring concrete pads for the future pumps on east side of the Clearwell
Getting outlet trench (temporary) opened to handle the drainage on the west side of the site
Working on the precast concrete coping at NE corner of the Clearwell tie into the corbel
SE corner of the Clearwell Reservoir for the level element, the east 24” FW piping and the suttle access hatch
Working on the sluice gate for the Chlorine and Ammonia Vault on the west end of the Clearwell
Contractor installing the deck shoring for the main floor access to the Clearwell
Getting ready to set shoring for patching the hole in the floor of the Clearwell west center area
Tying rebar mats in the Clearwell floor area, east side of the Chlorine / Ammonia Vault
Working on installing the steps in the Washwater Recovery Basin NW area
Cleaning up the floor area on the east side of the Chlorine / Ammonia Vault
Cleaning the floor area patch on the east side of the Chlorine / Ammonia Vault
Patch for floor area on north side of the electrical room in the Clearwell area
Floor drain in the floor area as shown on sht 4-S-2
Contractor has personnel grinding the floor area in the bottom of Clearwell in area where grout was installed to patch up area where slabwasundercylinderstrengthbreaks
Lifting pump #5 to be set in the Clearwell, SW corner
Swinging SW pump #5 to t he Clearwell SW pump corner
Lowering pump #4 into Clearwell
Lowering pump #4 into the Clearwell
Lowering pump #4 into the Clearwell, west side
Pump #4 west side being lowered thru the hatch
Setting pump #4 on the bolt pattern and grout (non-shrink)
Contractor pouring the floor patch
Contractor pouring the floor patch on the east side of the Ammonia / Chlorine Vault
The floor patch poured on the east side of the Chlorine / Ammonia Vault
Thumbnail panels:
|
|
|