| |
Construction Photos - Week of 02/13/09
Equipment being installed on the north wall of the electrical room
Door and louver removed from SW corner of the electrical room
Contractor setting the precast concrete coping in the NW corner of the Clearwell Finished Pump Station
Welds inside the piping on the east area for the future piping for surge bladder tank
Welds on the outside of the piping on the east area for the surge bladder tank
Flow Control Valve on site
Flow Control valves on site
Working on piping on east side of the Clearwell
Finishing the brick wall on the NW corner of the Clearwell Finished Water Pump Station
Piping set on the main line on the west side of the Clearwell / Finished Water Pump Station, east side, south half
Piping set on the west side of piping on the east half of the Clearwell Water Pump Station
Door and louver removed in the SW corner of the electrical room
Getting ready to weld the outside edge of the tee for the FCV and surge relief valve
Getting ready to weld the outside edge of the tee for the FCU and surge relief valve, looking inside the weld
Electricians crew getting ready to bring one of the electrical SBC-C-1 into electrical room
Moving electrical panel to the inside of electrical room after door and louver removed
Electrical panel set on the north wall of the electrical room on the housekeeping pad
Weld on the tee for the FCU and surge relief valve
The tee welded for the FCV and surge relief east side (SE corner of Clearwell)
Corking in the Chlorine Contact Basin on patching, grinding and cleaning
Getting ready to weld 20”x18” reducer in the Clearwell, west side Water Pump Station
Welding the 20” x 18” reducer in the Clearwell west side Water Pump Station
Getting everything set up for re-doing 20” x 18” reducer on the west piping tee
Getting it lined up for re-doing the reducer on the piping tree
Looking inside the west piping reducing 20” x 18” on water line in Clearwell looking north to soth
Everything lined up to start welding on the west side waterline
One of the welds from the side on the 20” x 18” reducer
Another picture of the weld on the 18” x 20” reducer west side
Welder welding on the 20” x 18” reducer on the west side of the Clearwell east side
Bending rebar for the concrete pads in the electrical room for electrical panels
Cutting rebar for pads in the electrical room
Working on the piping tree at the north end of the east piping tree for the east / west Clearwell Finished Water Pump Station
Holes for the stud anchors on the copings
Forming for equipment housekeeping pads in the electrical room
Middle equipment housekeeping pads in electrical room
Working on north end of the Clearwell Pump Station piping tree
Filling the roof joist opening that were left so the block work could be done first, before the roof?
Filling the roof joist opening that were left so the block work could be done first?
Cutting opening for the FE-6-4 as shown on sht 4-M-1 on the east water line
Tree at the north end of the west and east water line for NPW and PW
Tree at north end of the west and east water line in the Clearwell
Unable to get a better picture, still a picture of the north most tree for NPW and PW (north end of Clearwell)
Rebar in the bottom of the floor above in the lower level of the Clearwell, it appears to be rebar that close, unable to get a good pic
Rebar in the bottom of the floor above in the lower level. Still unable to get a very good picture
Patching around a column in the bottom of Chlorine Contact Basin
Installing the 8” FW piping as shown in section E/4M1, see sht 4-M-4
Installing the precast concrete coping at the NW corner of the Clearwell Finished Water PumpStation
Concrete truck on site with materials for pads for the electrical room
Welding certification personnel on site to certify the contractors welder
Placing concrete pad in the center of the electrical room
Finishing curb in the roof of the Contact Chamber NE corner (roof vent)
Pouring the scuttle hatch in the NE corner of the Contact Chamber
Picture taken from roof over the Contact Chamber (roof vent and scuttle hatch)
On knoll looking SE to the Washwater Recovery Basin
Looking south over the Clearwell Finish Water Pump Station
Looking SW past the west half of the Clearwell Finish Water Pump Station
Thumbnail panels:
|
|
|